Fulton Hogan Quarry, Tynong

Bulk Earthworks
MC Earthmoving began the development of a new pit at Fulton Hogan at their existing quarry site in Tynong North in 2016. This involved the removal of overburden, the subsequent remediation of the existing pit and the development of a new extractive source. Over the past four years this stripping and overburden campaign has seen MCE move in excess of two million BCM of waste material.
Quarrying
MC Earthmoving’s vast experience in quarrying activities and civil construction along with their ability to supply equipment and experienced operators, has enabled them to meet the increasing demands of Fulton Hogan.
Progress Note
Today, MC Earthmoving is contracted to provide both load and haul services for raw feed and the continual removal and placement of overburden and the rehabilitation of the existing pit while developing a new site foundation for the future.